DENR-EMB Permit to Operate (PTO) Guidelines

Republic Act No. 8749 – Philippine Clean Air Act of 1999

The Permit to Operate (PTO) is an environmental regulatory permit issued by the Department of Environment and Natural Resources – Environmental Management Bureau (DENR-EMB) for facilities operating air pollution sources and control installations.

For Crown Agarwood Processing Corp. (CAPC), this requirement is particularly relevant if the facility will operate:

  • Steam or hydro-distillation equipment.
  • Essential oil extraction equipment.
  • Supercritical CO₂ extraction systems.
  • Boilers and industrial heating systems.
  • Generators and other fuel-burning equipment.
  • Other machinery that produces regulated air emissions.

Important: Not every extraction machine automatically requires a PTO. Applicability depends on the equipment, its emission characteristics, applicable regulatory classifications, and EMB assessment.

1. Legal basis and implementing regulations

Legal issuancePurpose
RA 8749Philippine Clean Air Act of 1999
DENR Administrative Order 2000-81Implementing Rules and Regulations of RA 8749
DENR DAO 2004-26Amends Rule XIX on Permit Regulations
EMB Memorandum Circular 2007-003Classification of air pollution source installations and source emission testing
EMB Memorandum Circular 2020-17Guidelines for PTO issuance through the Online Permitting and Monitoring System (OPMS)
DENR DAO 2016-28Updated fees and charges for EMB services

Under Rule XIX, stationary sources of air pollution covered by the regulations must secure a valid PTO from the EMB Regional Director. DAO 2004-26 also removed the general Authority to Construct requirement under the earlier rules. However, consultation with EMB before installation or modification is encouraged. Supreme Court E-Library+2

2. Equipment covered by PTO requirements

The following equipment should be assessed for PTO applicability:

Equipment / operationPotential air emissions
Steam boilerParticulate matter, NOx, SOx, CO
Diesel generatorNOx, SOx, CO, particulate matter
Biomass-fired furnaceSmoke, particulate matter, CO
Steam distillationCombustion emissions from its heat source
Hydro-distillationCombustion emissions from its heat source
Supercritical CO₂ extractionPotential process-related emissions, depending on system design and releases
Solvent extractionVolatile organic compounds (VOCs), depending on solvent and process
Spray drying / heatingProcess emissions, depending on materials and equipment

Important distinction: A closed-loop CO₂ extraction machine does not automatically require a PTO simply because it uses CO₂. Its actual emission sources and applicable exemptions must be evaluated separately.

3. PTO exemptions and source classification

DENR-EMB Memorandum Circular 2020-17 provides the procedure for determining whether an air pollution source installation or equipment is exempt from securing a PTO.

The applicant should:

  1. Identify each air pollution source installation/equipment (APSI/E).
  2. Review Annex C of MC 2020-17 for exempted sources.
  3. Determine its source classification under MC 2007-003.
  4. Determine whether source emission testing is required.
  5. Apply through OPMS if the equipment is not exempt.

Exemption from PTO and exemption from source emission testing are different classifications. One should not automatically be interpreted as the other. Air Quality Management Section+2

4. Documentary requirements for a new PTO

The EMB application process generally requires the following:

No.Documentary requirement
1Accomplished PTO application through OPMS
2Engineering report describing the facility and equipment
3Equipment photographs with geotag or equipment brochure
4ECC or CNC, as applicable
5SEC Certificate of Registration or applicable business registration
6Valid Pollution Control Officer (PCO) accreditation
7PCO appointment/designation by the Managing Head
8Environmental Management Plan, where required
9Air Pollution Control Device (APCD) details, where applicable
10Stack sampling or source emission test results, where required
11Applicable application and permit fees

The engineering documentation should adequately identify equipment specifications, operating capacity, fuel consumption, emission sources, pollution control equipment and expected emission performance.

The precise checklist depends on the source classification and EMB Regional Office assessment. Environmental Management Bureau Region V+2

5. Application procedure through EMB-OPMS

  1. Equipment assessmentIdentify all stationary air pollution sources and determine PTO applicability.
  2. Prepare documentary requirementsComplete the engineering report, PCO documentation, ECC/CNC and equipment information.
  3. Register and submit onlineRegister and submit the application at EMB Online Permitting and Monitoring System.
  4. Technical evaluationEMB reviews the application and may request additional documents, validation or testing.
  5. Payment of feesSecure the Order of Payment and settle applicable fees.
  6. PTO approvalThe EMB Regional Director approves the application when requirements are satisfied.
  7. Display and complianceKeep the approved PTO accessible and comply with its operating and emission conditions.

Source: EMB Air Quality Management Section, OPMS PTO procedure. Air Quality Management Section+1

6. PTO validity, renewal and compliance

Under DAO 2004-26:

  • Regular PTO validity: five years from issuance, unless sooner suspended or revoked.
  • Renewal: file at least 30 days before expiration.
  • Transfer: notify EMB within 30 days of sale or legal transfer; the transferee must apply for transfer within 10 days after notification.
  • Equipment breakdown affecting compliance: notify EMB within 24 hours.
  • Monitoring: maintain operational and pollution-control records and submit required reports.

The actual permit conditions govern the allowed operating capacity and emission limits. For example, an equipment source tested and approved at a particular operating capacity may be restricted to that capacity. Supreme Court E-Library

7. Applicable fees and processing time

PTO fees are determined by the applicable EMB fee schedule and the number, type and capacity of the air pollution source installations and control devices.

The charges may include:

  • Application/filing fee.
  • Permit fee.
  • Documentary stamp tax.
  • Other applicable statutory fees.

The EMB OPMS procedure indicates a standard processing target of approximately 20 working days after the complete application and applicable requirements are received. Actual processing may depend on technical evaluation and deficiencies. Air Quality Management Section+1

8. Specific compliance recommendations for Crown Agarwood Processing Corp. (CAPC)

For an agarwood and botanical extraction facility, I recommend preparing an Air Pollution Source Inventory before applying.

EquipmentRecommended compliance preparation
Steam boilerFuel specification, rated capacity, stack information
Diesel generatorkW capacity, operating hours, fuel consumption
Biomass furnaceFuel type, combustion system, emission controls
Steam distillationHeating source and associated emission controls
Hydro-distillationBoiler/furnace specifications
Supercritical CO₂Closed-loop system specifications, venting and pressure-release arrangements
Solvent extractionSolvent inventory, VOC controls and ventilation
Air pollution control devicesEquipment specifications and control efficiency

Recommended supporting documents:

  1. Plant layout and equipment location plan.
  2. Equipment technical specifications and rated capacities.
  3. Process flow diagram.
  4. Fuel and solvent consumption estimates.
  5. Stack and emission-source inventory.
  6. Air Pollution Control Device specifications.
  7. Engineering report.
  8. PCO appointment and accreditation documents.
  9. ECC/CNC documentation.

These documents will also help establish whether separate PTO applications or a grouped application are appropriate.

9. Official DENR-EMB references

EMB Air Quality Management Section

PTO guidelines and application procedure

EMB Online Permitting System

Online PTO application

DENR-EMB Region IV-A (CALABARZON)

Regional PTO requirements and Citizen’s Charter

Supreme Court E-Library

DENR DAO 2004-26 – Permit Regulations

10. Recommended environmental permit sequence for CAPC

CAPC Environmental Compliance Framework

  1. ECC / CNCEnvironmental classification and coverage determination.
  2. PCO AccreditationDesignation and accreditation of the Pollution Control Officer.
  3. Permit to Operate (PTO)Authorization for applicable air pollution source installations.
  4. Wastewater Discharge PermitIf the facility discharges regulated wastewater.
  5. Hazardous Waste Registration and ComplianceIf the facility generates hazardous waste.
  6. Continuing Environmental MonitoringEmission testing, monitoring reports and compliance with permit conditions.

The above permits and registrations are subject to the facility’s actual environmental coverage and activities.