DENR-EMB Certificate of Non-Coverage (CNC) for Distillation and Extraction Facilities

A Certificate of Non-Coverage (CNC) may be relevant when establishing an agarwood distillation, essential oil extraction, or botanical processing facility in the Philippines.

First, a terminology clarification: CNC means Certificate of Non-Coverage, not Certificate of Non-Compliance.

A CNC is issued by the Department of Environment and Natural Resources – Environmental Management Bureau (DENR-EMB) when a proposed project is determined not to be covered by the Philippine Environmental Impact Statement (EIS) System, subject to the applicable project classification and conditions.

It is not a general environmental operating permit and does not automatically exempt a facility from other environmental requirements.

1. Does an agarwood distillation facility qualify for a CNC?

Not automatically. DENR-EMB must screen the proposed facility under EMB Memorandum Circular No. 2014-005 and applicable amendments.

For CAPC, the following activities should be disclosed:

Proposed activityCNC screening consideration
Agarwood chip preparationProcessing activity
Steam distillationEssential oil extraction
Hydro-distillationBotanical extraction
Supercritical CO₂ extractionIndustrial/botanical extraction
Oil filtration and purificationPost-extraction processing
Aroma fractionationSpecialized processing
Perfume formulationManufacturing activity
Packaging and storageAncillary facility activity

The facility’s capacity, equipment, fuel consumption, wastewater generation, emissions, site location and proximity to environmentally critical areas can affect its classification.

Important: Do not describe an industrial extraction facility merely as an agricultural plantation or small laboratory if it will actually operate as a commercial processing plant.

2. Documentary requirements

For a Category D CNC application, the 2025 EMB Citizens’ Charter identifies these standard requirements:

  1. Project Description for CNC application.
  2. Valid government-issued identification.
  3. Notarized Accountability Statement of the Proponent.
  4. Recent photographs of the project area (taken within 15 days of filing).
  5. Site Development Plan signed by a professional.
  6. Proof of payment, where applicable.

For Category C or special manual applications, EMB CALABARZON has a separate procedure and documentary checklist. EMB CALABARZON

3. Application procedure

  1. Project coverage screeningVisit the official DENR-EMB CNC online screening system. EMB CNC Online Application
  2. Enter project informationProvide the project name, location, project type, and detailed activity description.
  3. Determine environmental classificationThe system determines whether the project is Category D or requires further EMB evaluation.
  4. Submit CNC applicationUpload the required documents and complete the application.
  5. Pay applicable feesFollow the payment instructions in the online system.
  6. Download the approved CNCThe online system advises that the approved CNC may be downloaded within five working days after proof of payment is attached, subject to application processing and approval.

4. Other environmental permits CAPC may need

A CNC does not replace the following permits where applicable:

Environmental requirementWhen applicable
Permit to Operate (PTO)Boilers, furnaces, generators and other regulated air pollution sources
Wastewater Discharge PermitWhen wastewater is discharged to a receiving body of water or other regulated discharge point
Hazardous Waste Generator IDWhen the facility generates regulated hazardous waste
Pollution Control Officer (PCO)If required under applicable EMB regulations
Environmental monitoring and reportingDepending on permits and regulatory classification

Official CALABARZON permitting information:

5. Recommended CNC project description for CAPC

Proposed project title: Crown Agarwood Processing Corp. – Agarwood Distillation, Essential Oil Extraction and Botanical Processing Facility

Suggested project description:

The proposed project involves the establishment and operation of an agricultural botanical processing facility specializing in the preparation, distillation, extraction, purification, and processing of agarwood and other legally sourced botanical raw materials.

The facility will utilize appropriate processing technologies, including steam distillation, hydro-distillation, and supercritical carbon dioxide (CO₂) extraction, for the production of essential oils, botanical extracts, aromatic concentrates, and other value-added botanical products.

Ancillary activities include raw material preparation, drying, filtration, separation, fractionation, quality control, packaging, and finished-product storage.

The facility will implement appropriate environmental management measures for air emissions, wastewater, solid waste, hazardous waste, chemical handling, and resource conservation, consistent with applicable DENR-EMB regulations.

This is a draft description, not a determination that the facility qualifies for CNC.

6. Information needed to prepare the actual application

I recommend preparing a project-specific CNC application package for CAPC rather than submitting a generic description.

CAPC facility details

1. Facility location

2. Extraction technologiesSteam distillationHydro-distillationSupercritical CO₂ extractionSolvent extractionFractionation and purification

3. Facility capacitySmall commercial facilityMedium-scale facilityLarge industrial facilityPilot laboratory

4. Steam boiler / heat sourceBiomass-firedLPG-firedElectricNo boiler

5. Wastewater managementWith wastewater treatmentClosed-loop water recyclingNo wastewater dischargeNot yet determinedPrepare CAPC CNC application package

My recommendation is to obtain EMB’s project coverage determination before finalizing equipment procurement or facility construction. This will help establish whether CAPC should apply for a CNC or an ECC and identify the separate environmental permits required.